Manganese in Gabon: From Mine-to-Port Railway to Metallurgical Complex

Gabon’s manganese story turns on a transport link, shifting ownership and a bid to process ore at Moanda. The figures trace an expanding industry, but do not by themselves identify what drove each change.

Business

Gabon

Gabon
Map of Africa highlighting Gabon

Origins

Gabon’s manganese industry began with a deposit and a logistical problem: how to get ore from Moanda to a market. According to COMILOG’s company history, manganese indications were reported at Moanda in 1944. The history of COMILOG’s exploration, as summarized in the 1966 article “Le manganèse du Gabon” in Persée, includes joint prospecting by the Bureau minier d’Outre-Mer and U.S. Steel geologists from 1951 to 1953. The company was constituted in September 1953 to continue exploration and address transport, with mining and marketing among its contemplated activities. These early dates come from those publications, rather than from the verified decisions below.

Commercial production began in 1962, according to the World Bank’s Gabon report and COMILOG’s company history. The initial route, described in those sources, carried ore by cableway to Congo and then by rail to Pointe-Noire. That arrangement made transport a defining feature of the industry from its start: production at Moanda depended on a route beyond the mine and across national borders. Later, Gabon’s railway and port decisions would create a route to the country’s own coast.

The World Bank’s merchandise-export indicator offers one measure of manganese’s early place in Gabon’s trade, but it covers minerals and metals together, not manganese alone. In 1962, minerals and metals represented 17.65 percent of merchandise exports; the share reached 40.14 percent in 1966, then stood at 13.68 percent in 1970. These figures document large changes in the category’s share of exports, not the contribution of manganese specifically. They also do not say what caused those changes.

The decisions that shaped it

Figures around a decision give context and do not by themselves prove its effect. The measures used here also cover different things: production volumes are not export shares, and national export or GDP indicators are not manganese-only measures. In particular, the U.S. Bureau of Mines’ gross-weight production figures below come from a table of annual production; they should not be compared directly with the USGS figures, which use thousand tonnes.

In 1986, the state-backed Trans-Gabon Railway began carrying Moanda ore toward Owendo, near Libreville. COMILOG’s company history says the railway provided a route from the mine to the port; its impact was to enable transport to Gabon’s own port. As production context, the U.S. Bureau of Mines reported 2,339 thousand tons, gross weight, of Gabonese manganese ore and concentrate in 1985 and 2,404 thousand tons in 1987 in “Manganese Availability—Market Economy Countries: 1980’s Perspective.” Those are two figures from that publication, not evidence that the railway caused an increase. The series gives 2,510 thousand tons for 1986, but the figures alone cannot isolate the railway’s contribution.

The state’s next transport milestone was the 1988 inauguration of Owendo’s mineral port. COMILOG’s history describes the port as the coastal endpoint complementing the railway route from Moanda. The nearest production observation in the cited Bureau of Mines publication is 2,404 thousand tons, gross weight, for 1987; that publication does not provide a later observation. Separately, the World Bank reports minerals and metals at 18.34 percent of merchandise exports in 1978 and 5.12 percent in 1982. Those earlier trade figures precede both infrastructure decisions; they are context, not a measure of what the railway or port changed. COMILOG’s company history supports the route’s intended function, but the cited figures do not quantify its effect.

In 1996, Eramet became COMILOG’s principal shareholder, according to the company history. The change placed Eramet in the lead shareholder and industrial-operator position at Gabon’s principal manganese producer. The World Bank’s minerals-and-metals share of merchandise exports was 3.41 percent in 1994, 2.03 percent in 1996 and 5.72 percent in 1997. This indicator covers all minerals and metals, not COMILOG or manganese alone; its movement around the ownership change cannot establish an effect of the change. COMILOG’s company history establishes Eramet’s position, but does not give later ownership percentages with which to trace how that position evolved.

In 2009, COMILOG laid the foundation stone for the Moanda Metallurgical Complex, with investment scheduled over 2009–2013. The company described the planned complex as a way to create value in Gabon, producing silicomanganese through pyrometallurgy and manganese metal through hydrometallurgy. National trade figures give context: the World Bank’s minerals-and-metals category accounted for 3.03 percent of merchandise exports in 2009 and 2.49 percent in 2010. Its separate measure of exports of goods and services as a share of GDP was 52.17 percent in 2009 and 57.66 percent in 2010. Neither indicator isolates manganese or measures the project’s effect. They show the wider trade setting as the investment was announced, not its results.

In 2010, the Gabonese Republic and COMILOG agreed to raise the state’s participation in the company to 27.6 percent. COMILOG’s history records the agreement and the resulting share. The move changed the state’s ownership stake; The cited account of COMILOG’s history records the agreement and resulting share but does not establish whether there were further changes to management, operations or the distribution of returns. The nearby World Bank trade observations remain broad national measures: minerals and metals made up 2.49 percent of merchandise exports in 2010 and 3.86 percent in 2011. Those shares cannot show the effect of the ownership agreement. Nor do they indicate the state’s financial gains from the stake.

In 2014, COMILOG recorded its first silicomanganese production at Moanda, followed in 2015 by the inauguration of the Metallurgical Complex. The first production marked a move beyond ore and agglomerate toward a locally produced manganese alloy; the complex’s documented project design also included manganese metal. USGS Minerals Yearbook—Manganese production data put Gabon’s manganese output at 3,781 thousand tonnes in 2014 and 4,112 thousand tonnes in 2015; the figures are gross-weight production, not silicomanganese output. The World Bank’s minerals-and-metals share of merchandise exports was 1.09 percent in 2014 and 1.58 percent in 2015. Neither measure isolates production or sales from the new complex, so neither establishes how much the first production or inauguration changed overall output or exports.

The next three production observations show how output moved after the complex’s opening, without identifying what drove it. USGS Minerals Yearbook—Manganese records 3,379 thousand tonnes in 2016, 4,717 thousand tonnes in 2017 and 5,071 thousand tonnes in 2018. COMILOG’s history says 2018 was its first production record above 4 million tonnes. The World Bank’s minerals-and-metals share of merchandise exports was 1.83 percent in 2016 and 3.12 percent in 2018. The production series measures Gabonese manganese output; the export indicator includes other minerals and metals. Their different coverage means they should not be treated as parallel measures of the complex’s performance.

Who holds the levers

The decisions locate three central actors: the Gabonese state, COMILOG and Eramet. The state’s documented role is twofold: infrastructure, through the railway and port route, and ownership, through a 27.6% stake. It backed the railway and Owendo port route and, with COMILOG, signed the agreement that raised the Republic’s stake to 27.6 percent in 2010. The cited account of COMILOG’s history establishes those actions but does not establish the state’s broader regulatory powers or the terms of its participation beyond the percentage.

COMILOG is the company at the centre of the production and investment decisions. It carried the Moanda Metallurgical Complex project, recorded the first silicomanganese production and inaugurated the facility. Its company history describes the complex’s intended products and the railway’s transport function. The cited account of COMILOG’s company history does not establish a breakdown of the complex’s output or the share of Gabon’s overall production processed there.

Eramet’s verified role is as COMILOG’s principal shareholder from 1996. The cited account of COMILOG’s company history identifies that position but does not establish Eramet’s current ownership or control over individual decisions. COMILOG’s company history traces a shift in shareholder status, but does not establish who exercises each operational or public-policy lever today.

Where it stands today

The latest manganese production figure in the USGS Minerals Yearbook—Manganese series is for 2023: 9,968 thousand tonnes, gross weight. Output in the same USGS series was 10,375 thousand tonnes in 2022, so the 2023 figure was lower; it was still well above the series’ 3,781 thousand tonnes in 2014. These observations describe production volume, not the share processed in Gabon, the value of sales or the profitability of the sector. They also do not establish why output changed.

The latest available World Bank observation for minerals and metals as a share of merchandise exports is 23.31 percent in 2023. It was 6.43 percent in 2022. The sharp difference is notable, but the indicator’s broad category means it cannot be read as manganese’s share of exports, and the World Bank series does not explain the change. For a wider economic setting, World Bank exports of goods and services equalled 55.49 percent of GDP in 2025, while nominal GDP was about US$21.4 billion in current dollars that year. Those are country-level figures, not measures of the manganese industry.

The record therefore supports a clear account of the sector’s main structural changes: an early cross-border route, a railway and port route within Gabon, a change in COMILOG’s principal shareholder, a larger state stake and the addition of a local metallurgical complex. The latest data show substantial manganese production and a high minerals-and-metals share of merchandise exports in 2023. They do not, on their own, show how much value the complex retains in Gabon, how ownership returns are divided or what portion of recent export changes came from manganese.

What to watch

The available sources point to several useful measures, not to predictions. First is the next observation in the USGS production series: it would show whether the 2023 fall from 2022 continued or reversed. Second is the World Bank minerals-and-metals share of merchandise exports, especially whether the 2023 reading of 23.31 percent persists. Because that indicator is not manganese-specific, it should be read alongside manganese production rather than as a substitute for it.

A third test is the local-processing ambition set out for the Moanda Metallurgical Complex. The verified decisions establish the complex’s intended production of silicomanganese and manganese metal, and the first silicomanganese production in 2014, but COMILOG’s company history does not report output by product. Product-level production data would help distinguish ore extraction from local transformation. Finally, the state’s 27.6 percent participation and Eramet’s principal-shareholder status are documented at specific moments, not as a current ownership picture. Later ownership information would clarify how the distribution of formal stakes has changed since those decisions.

Deep Eye

Decisions that shaped the sector

  1. Trans-Gabon Railway begins carrying Moanda oreSource: Comilog, “Histoire”
  2. Owendo mineral port inauguratedSource: Comilog, “Histoire”
  3. Eramet becomes COMILOG’s principal shareholderSource: Comilog, “Histoire”
  4. Moanda Metallurgical Complex construction beginsSource: Comilog, “Histoire”
  5. Gabon agrees to raise its COMILOG stake to 27.6%Source: Comilog, “Histoire”
  6. First silicomanganese tapped at MoandaSource: Comilog, “Histoire”
  7. Moanda Metallurgical Complex inauguratedSource: Comilog, “Histoire”

Production over time · manganese

thousand tonnes · 2014–2023
U.S. Geological Survey (USGS), Minerals Yearbook — Manganese

Production figures from cited sources · manganese

Figures taken from different publications, each checked on its source page. They are not a continuous series.
YearProductionSource
19762,216 thousand tons, gross weightU.S. Bureau of Mines, “Manganese Availability—Market Economy Countries: 1980’s Perspective”
19802,146 thousand tons, gross weightU.S. Bureau of Mines, “Manganese Availability—Market Economy Countries: 1980’s Perspective”
19852,339 thousand tons, gross weightU.S. Bureau of Mines, “Manganese Availability—Market Economy Countries: 1980’s Perspective”
19872,404 thousand tons, gross weightU.S. Bureau of Mines, “Manganese Availability—Market Economy Countries: 1980’s Perspective”
The Briefing · free, weekly

One decision, its figures, and what it changes — every week.

The 54 Eyes follows the decisions of governments, regional blocs and companies through to the African economies they affect. The briefing brings you the week’s most consequential ones, with the sources.

No bought lists, no daily noise. Unsubscribe in one click.
Intelligence context

What this story changes.

GeographyGabon
SectorIndustries Extractives
FormatDeep Eye
Evidence3 sources